Freestone Pipeline Project

11.2 miles of 20” OD steel gas line

5.6 miles of 14” PVC water discharge line

Meter / regulator station, filter separator, scrubber, storage tank, and inlet pipeline

Pig launcher and receivers

Directional drilling of the Trinity River


Deer Park Energy Center

Two 20” OD gas pipelines, 6400 lineal feet each

Meter / regulator station, filter separator, scrubber, storage tank

Pig launchers at the meter site.

Pig receivers, regulation facilities, filter separators, scrubbers, and storage tank at the Deer Park Site

Two Directional drills – 1600’ long each


30” Bammel to Hempstead Highway Line

12.7 miles of 30” gas pipeline

Meter / regulator station at each end.

Directional drills


16” and 18” Tom O’Connor to Edna Line

Cleaned and Hydrostatic tested 40.8 miles of 16” pipeline and 10.7 miles of 18” pipeline.


Bammel Storage 20” Injection and Recovery System


Bridgeport Compressor Station and Pipeline


Kinder Morgan Compressor Station #388


West Bammel Meter Skid, Main Line Valve and Crossover Line


Retire 24” Houston West Loop Line Piping


West Bammel 30” Meter Skid and Regulator Station


Hempstead Highway, Katy Satsuma 30” Main Line Valve, Tee, and Blow Down


Katy Meter and Regulator Station


EOG/HPL Westfield 6” Pipeline and Meter Station


Conroe to FM 1960 Line Conversion to Natural Gas


Houston Pipe Line / Enron

16" Tom O'Conner Pipeline cleaning and up-rating - Edna to Refugio, TX


Houston Pipe Line / Enron

16" Valley Pipeline cleaning and up-rating - Alvin to Wadsworth, TX


Enron Midstream / Crestone Energy Ventures

Coal Seam grass roots gathering system - Gillette, WY


Calpine / AWGE - Baytown Energy Center

3 miles of dual pipeline and 4 metering stations - Baytown, TX


Calpine - St. Gabriel Energy Center

Pipeline and meter station for power plant - St. Gabriel, LA


Tractebel / AWGE - Wise County Power Plant

Install two 3500 VFD Electric Drive Compressors and

associated equipment and piping


 Calpine

Installation of 12 miles of 12" pipeline in Rio Vista, CA


Calpine

Installaion of 8" pipeline in Pittsburg, CA


Brazos Valley Power / AWGE

Installation of pipeline and compressor station

for power plant in Jack County, TX